Menu

Australian Shares.com is the world's biggest free online database of information on Australian resource companies.

This website has up-to-date details on over 1000 separate listed and unlisted organisations, including what they mine (or explore) for, how much of any given resource they have in the ground, or in reserve, the location of their operations, corporate details, news, links and history. Find out more

Australian Shares

Australian Shares Sparty's Blog

Comments on this blog should never be taken as investment advice


Posts on this website are general "tips" and nothing more than that and should never be used to make an investment or trading decision. All information should be carefully cross-checked against official sources for accuracy. Sparty's posts nearly always relate to companies that he either holds, has held or intends to hold.

Main ForumGALAXY JIANGSU LITHIUM CARBONATE PROJECT UPDATE

  • GALAXY JIANGSU LITHIUM CARBONATE PROJECT UPDATE

    Galaxy Resources Limited (ASX: GXY, Galaxy) advises that final-stage construction of the Jiangsu Lithium Carbonate Project (the Project or Jiangsu) continued on schedule during August 2011, with good progress made in all areas.

    Galaxy said the construction workforce currently totalled 350 people, with an expected ramp up to 450 during September 2011. During August, solid progress had been achieved in all areas with all tanks and bins delivered and installed on site. Equipment installation, structural steel and pipework installation also progressed according to schedule.

    High voltage cable and switchgear installation was completed and cable tray installation commenced.

    During the month, the kiln contractor was replaced (from MCC1 to CN 2,3). Productivity significantly improved with the kiln contracting workforce

    increasing from 28 to 110 people. There was some minor time lost due to typhoon Muifa and local flooding.

    Galaxy Resources Managing Director, Iggy Tan said good progress had been achieved at the Jiangsu site with the project developing according to the previously-announced schedule.

    "We are pleased with the progress being made towards the commissioning of the Jiangsu Project. Construction workforce levels have markedly improved and will continue to increase. Pleasingly, project costs are also in line with expectations", Mr Tan said. Ends

    As a long term investor in GXY I am pleased with progress and look forward to the value add (3x) that the new plant will provide. As can be seen from the graphic below there is a lot more to come re value adding.

Want to take part in this discussion? Click one of these: Sign In Apply for Membership

Australian Shares Forum Options

 








Howdy, Stranger!

It looks like you're new here. If you want to take part in the discussions, click one of these buttons!

Sign In Apply for Membership